Creation of the industrial park Starokorsunsky

Project nameCreation of the industrial park Starokorsunsky
Industry classificationManufacturing industry
Basic information about the project
Project essenceThis project involves the construction of an industrial park Starokorsunskaya at: Krasnodar, Starokorsunskaya village in the Karasunsky inner city district of the city of Krasnodar
Project capacityThe volume of production per month: 24416 tons of products (dairy, meat, greenhouse complex products, refrigeration plant products, glass and cardboard packaging products, feed mill products, brewery products, feed mill products and others)
Consumer market descriptionIndividual persons, legal entities in Krasnodar and Krasnodar Region, other regions representatives, export.
Object construction term6.00
Competitive advantageIn General terms, competitiveness can be represented in the following way: - high technical level of the product; - the level of marketing, advertising and information support; - compliance with the requirements of the consumer: - organization of the service; - cooperation of fabrications in the territory of an industrial park; - delivery time of products; - price, terms of payment.
Resource availability for project realizationProvision of raw and other materials is carried out by the investor
Planned volume of resource consumption (annual)
Planned volume of electricity consumption (annual), MWh219.00
Planned volume of gas consumption (annual), million cubic meters40.00
Planned volume of water consumption (annual), million cubic meters0.90
Degree of project developmentBusiness plan is worked out, town-planning and design estimates documentation are being developed
Financial estimation of the project
Total cost of the project, mln rubles35100.00
Own resources, million rubles0.00
Means of regional (municipal) budget, million rubles0.00
Previously involved means, million rubles.00
Investment capacity, mln rubles35100.00
Conditions of investor participationDirect investments
Form of investments returnMonetary
Payback period9.50
Basic indicators of investment project economic efficiency
Net present value (NPV)2366.60
Simple payback time9.50
Discounted payback period13.30
Internal rate of return (IRR)14.00
Productivity index (PI)1.45
Income per year 15252.00
Social efficiency of investment project
Number of workplaces80
Salary average level (thousand rub per year)251.25
Budgetary efficiency of investment project
Mid-annual tax payments, million rubles3000.00
which includes into consolidated budget of the krai, million rubles300.00
General information about the ground area
Address of the areaRussia, Krasnodar region, Krasnodar city, Karasunsky city district, village Starokorsunskaya.
Cadastre account of ground areaRegistered
Cadastre number of area/of quarter23:43:0424001:231, 23:43:0424001:210, 23:43:0424001:230, 23:43:0424001:229, 23:43:0424001:213, 23:43:0424001:212, 23:43:0424001:208, 23:43:0424001:226, 23:43:0424001:207, 23:43:0424001:189, 23:43:0424001:193, 23:43:0424001:201, 23:43:0424001:178, 23:
Declared area (m2)2510000.00
Limit size of the area (m2)2510000.00
Land categoryIndustrial land use
Kind of allowed useProduction
Actual useIs not used
Availability of buildings, structures, constructionsNone
Permits, town-planning documentationIn accordance with the Masterplan land plot is situated in production and industrial area. In accordance with the land use and development rules the land plot is in industrial area ().
Information about proprietor (right holder)
ProprietorOOO UK Industrialniy park Starokorsunskiy
Right holderOOO UK Industrialniy park Starokorsunskiy
Kind of rightConstant (termless) using
Information about encumbrance and limitation
Kind of encumbrance, limitationNone
Encumbrance area.00
Electricity supply
Power supply center (name, right-holder)The projected energy center for gas electrogeneration OOO UK Industrialniy park Starokorsunskiy
Power supply center (electrotension class)Middle class of tension from 1 kV to 35 kV
Power supply center (free power (MWt))20.00
Power supply center (distance(m))0.00
Nearest connection point (network tension, kV)10.00
Nearest connection point (distance(m))0.00
Gas-supplying
Gas pipeline (name, right-holder)High pressure gas pipeline, DN 500, "Glass factory h. im. Lenina" AO "Gazprom gas distribution Krasnodar"
Gas pipeline (diameter(mm))500.00
Gas pipeline (pressure(MPa))High pressure pipelines of the II category from 0,3 to 0,6
Gas pipeline (carrying capacity(cube. m.in a year))40000000.00
Gas pipeline (distance(m))0.00
Nearest connection point (diameter(mm))315.00
Nearest connection point (pressure (MPa))High pressure pipelines of the II category from 0,3 to 0,6
Nearest connection point (carrying capacity (cubic meter a year))0.60
Nearest connection point (distance(m))0.00
Water-supply
Water supply source (name, right-holder)OOO UK Industrialniy park Starokorsunskiy
Water supply source (power (cubic meters a day))2550.00
Water supply source (quality of water)Service and drinking water
Water supply source (distance(m))0.00
Nearest connection point (power (cubic meters a day))2550.00
Nearest connection point (diameter(mm))225.00
Nearest connection point (distance(m))0.00
Sewage system
Type of building (name, right-holder)OOO UK Industrialniy park Starokorsunskiy
Type of building (power (cubic meters a day))2550.00
Type of building (distance(m))0.00
Nearest point of connection (power (cubic meters a day))2550.00
Nearest point of connection (diameter(mm))200.00
Nearest point of connection (distance(m))0.00
Installation of telephones/internet
Central network (distance(m))200.00
Mobile communication (distance(m))0.00
Rated price of the ground area supplying with engineering, mln.rub2590.00
Distance to the large settlements and objects of a transport infrastructure
Remoteness fromNameDistance (km)
center of municipal formation Krasnodar12.00
nearest settlement  0.00
Center of federal subject Krasnodar city0.00
highways (regional, federal value) Temryuk Krasnodar - Kropotkin0.00
highways of local value  .00
nearest railway station 113 km1.00
nearest railway SKZHD0.00
airport Krasnodar airport10.00
seaport seaport Novorossiysk170.00
Additional information about the ground area
Special conditionsThe estimated cost for the land will be 8 10 million rubles per hectare.
Cost of rent/buy of the ground area, mln. rub8.00
Geographical coordinates of object (dd.dddddd)
Latitude (N)45.05990000
Longitude (E)39.29150000
Data on the project initiator (in case of existence information about the legal/physical person)
Name / Full namePavlinov Anton Sergeevich
Postal address350062, Russia, Krasnodar Region, Krasnodar city, ul. Atarbekova, 1|1, office 15
Siteymanohin@yandex.ru
Phone/fax+79186773865
E-mail addressymanohin@yandex.ru
Data about the applicant (executive authority/local government executive authority)
NameDepartment for Economic Development, Investment and Foreign Affairs of Krasnodar City Municipality Administration
Postal addressKrasnodar City, Krasnaya str. 122.
Sitehttp://investment.krd.ru
Phone/fax(861) 218-95-50
E-mail addressplan@krd.ru
Executive (Full name, work position, phone number)Elena S.Vasilchenko, Director of the Department of Eco-nomic Development, Investment and Foreign Relations of the Administration of Krasnodar City